How should the contract specify the schedule and delays?

How should the contract specify the schedule and delays?

Do not write only the total number of days; instead write "milestones + trigger conditions": the measurement completion date, the plan confirmation date, the production start date, and the on-site arrival date, each with its corresponding prerequisite. The extension clause in particular must clearly state which situations count as extensions (plan changes, site not ready for installation); otherwise, responsibility cannot be determined when delays occur.