When during renovation should I schedule a whole-house customization measurement?

When during renovation should I schedule a whole-house customization measurement?

Don't wait until hard finishing is fully wrapped up before thinking to book it. The safer sequence is to book the re-measurement after water and electrical positioning is complete, because the sink water supply and drainage, gas outlet, and range hood exhaust path all need to be settled first. Our on-site measurement is usually arranged within 1–7 days; during measuring we also confirm wall flatness, kickboard, and internal and external corners, then decide the closing method. So it's advisable to get in touch after demolition and alteration are done and the water and electrical handover is complete—don't wait until tiling is finished to schedule. (On-site measuring is free; no measuring fee is charged.)